Taking over – it really matters

One of most the relevant milestones in the life of a wind farm is the taking over.

It happens when the contractual requirements for the wind farm are considered fulfilled by the subcontractor, except for smaller items that are noted in a “punch list” and have to be fixed as soon as possible.

The requirements for taking over are defined in the contract. They usually include a (very, very long) list of documents to be provided and all the tests to be performed.

The taking over is officialised by a taking over certificate. From this point delay liquidated damage stop accruing, and usually there is a reorganization of the bond structure (for instance the performance bond can be replaced by a warranty bond).

Additionally the clock for the defects liability period start ticking. Subcontractors have the obligation to replace defective items or equipment (for instance, a transformer) and this usually “reset” the clock for that specific equipment.

The obligations of the subcontractor are usually guaranteed by retention of payments for the punch list items and by the warranty bonds for the defect liability period.

Under FIDIC and FIDIC-like contract the subcontractor can make a claim if he consider that the employer is avoiding to issue the taking over certificate without a justified reason. This is particularly relevant if delay liquidated damages are accruing – in this case an independent third party expert is usually involved to solve the dispute.

“Sectional taking over” is another relevant concept – it means that the wind farm is not taken over as a whole but in smaller sections. Usually those sections match the wind farm internal circuits, but in theory even a single wind turbine (or even a foundation) can be taken over.

“Deemed taking over” means that if certain events happen (for instance, the wind farm start its operation) or a number of months elapse for when the takeover certificate is requested by the subcontractor the taking over is consider to have happened

One response to “Taking over – it really matters”

  1. Molla Kiros Avatar
    Molla Kiros

    Hi!
    Dear Francisco,
    I found all the explanations you mentioned. However ,i need more elaborations regarding the takeover process of an off-shore wind farm.

    Molla K

Leave a Reply

Your email address will not be published. Required fields are marked *